Wind Turbine Installation in the UK: Step by Step
Installing a small wind turbine takes a few days on site, but the steps before it usually take a few months. Here is the typical sequence.
- Site assessment – wind speed, turbulence, ground conditions, access and cable route. Start with a WindScore.
- Design and quote – turbine size, mast height, foundation and electrical design.
- Planning permission – usually 8 to 13 weeks for small turbines.
- Grid connection – a G98 notification, or a G99 application approved before installation.
- Groundworks – foundation pour, which needs time to cure, plus the cable trench.
- Erection – tilt-up masts for smaller turbines, crane lifts for larger ones.
- Commissioning – electrical testing, MCS certificate and grid paperwork.
Get an instant budget cost using WindQuotes. Wind speed, turbine size, cost and payback for your postcode in 60 seconds.
Get my budget price → Choosing an installer
Use an MCS-certified installer if you want to earn export payments, and ask for references for the same turbine model. Ask how they assessed your wind speed and turbulence, and what is included in servicing.
How long does it take?
Expect three to six months from first enquiry to switch-on for a home turbine, and longer for farm turbines that need a G99 study.