Every wind turbine that runs in parallel with the grid must be approved by your Distribution Network Operator (DNO). Which route you follow depends on the size of the turbine.
Turbines up to 16 A per phase (about 3.68 kW single-phase, or about 11 kW three-phase) can usually connect under G98. The installer notifies the DNO within 28 days of commissioning.
Larger turbines need a G99 application, and approval must be in place before installation. The DNO checks whether the local network can accept the extra generation. In some areas this needs reinforcement work, which can add significant cost or time, or an export limit.
On farm and business projects, grid capacity can make or break the scheme. It is worth getting a budget connection cost at the same time as your turbine price. GridQuotes can price and manage the DNO application for you, with every application signed off by a Chartered Electrical Engineer.